Fill a glass from a kitchen tap in Manchester and some of the water in it was probably in the Lake District a day or so ago. It got to you without a single pump. For 96 miles, from Thirlmere to Heaton Park reservoir in Prestwich, it ran downhill at walking pace. The Institution of Civil Engineers puts it at about 6 kilometres an hour, and just over a day from one end to the other.

An inch every hundred yards

The Thirlmere Aqueduct is the longest gravity-fed aqueduct in Britain, by the ICE's account. It falls about 20 inches in every mile, which is roughly an inch every hundred yards. Hold that gradient for 96 miles across Cumbria and Lancashire, over rivers and under fells, with Victorian levels and a lot of men with shovels, and the water arrives. Get it wrong anywhere and it stops.

Manchester went looking in the 1870s because its Longdendale reservoirs could not keep up with the city. John Frederick Bateman, the Corporation's engineer, pointed it towards the Lakes. Only three of them sat high enough to reach Manchester by gravity, and Thirlmere had one more thing going for it. It lies just below the pass of Dunmail Raise, so getting its water south of the watershed was the easier job.

The route is a mix of tunnel, cut and cover channel and cast iron pipe. The first tunnel, under Dunmail Raise, is the longest. Two teams drove it from opposite sides, and the ICE records that they met within 20 centimetres of each other.

The first fight of its kind

What Manchester did not plan for was the opposition. The Thirlmere Defence Association formed at Grasmere in 1877, and the Science Museum Group lists Thomas Carlyle, Matthew Arnold and William Morris among its members. John Ruskin's list of supporters from an earlier railway protest gave it a head start, and Octavia Hill lent it campaigning experience. It was the first organised campaign of its kind in the Lake District.

They lost. The Lords threw out the first Bill in 1878 on a technicality, but the second received Royal Assent on 23 May 1879. They did not lose everything, though. The committee that heard the evidence accepted that the public had "an inheritance in the beautiful scenery", and Manchester had to concede that the lake would never be drawn below its natural level. From then on a promoter had to answer for the landscape as well as the engineering. I think of that every time a planning inquiry runs long.

Six years of nothing, then the contractor stops

Having won its Act, Manchester did nothing with it for nearly six years. The council only approved a start in January 1885. Digging on the aqueduct was under way by April 1886, and by February 1887 the original contractor had suspended work and the contract had to be re-let. The Dunmail Raise tunnel was through in July 1890, and only then could the dam begin. The BBC, marking the 120th anniversary, put the job at eight years and about 3,000 men.

Water was let into the aqueduct on 12 October 1894, and the next day it rose from a fountain in Albert Square.

It was not a triumph on day one. Only one pipe had been laid, and by one account about a fifth of what went in at the top leaked out on the way. But the tunnels and channels had been built for far more than one pipe could carry, and that is the clever part. A second pipe came into use in 1904, a third in 1915 and a fourth in 1927. Each one added supply as the city grew, and nobody had to go back and dig the hard parts twice.

Not everybody gained. The hamlet of Wythburn sat largely above the new waterline but did not survive the scheme, and its churchyard was closed. From 1907 Manchester planted conifers on both banks, and people complained that they could no longer see Helvellyn from the road.

The next one

A second aqueduct, from Haweswater, followed in the 1950s. It is now 70 years old, and United Utilities is replacing all six of its tunnel sections under the Haweswater Aqueduct Resilience Programme. The estimated cost is about £3 billion, the build is planned to run for nine years, and around 1,200 people will be working on it at the peak. The originals were dug by hand and blasted. The replacements will be driven by tunnel boring machines.

Thirlmere is still in service, more than 130 years on. Nobody thinks about it, which is the point. The best infrastructure is the kind that works so quietly we forget somebody had to fight for it, price it, re-let it and dig it.