National Grid Electricity Transmission has started main construction on a new 400kV substation near Woolavington in Somerset, trade title E&T reported this week, part of the grid connection for Agratas' battery gigafactory on the Gravity Smart Campus near Bridgwater. Balfour Beatty, which carried out early site works from September 2025, is delivering the main build, with completion expected in summer 2029.
Because the substation will not be ready in time for the gigafactory's planned start of production, National Grid Electricity Distribution has already built two interim 33kV connections to keep Agratas supplied in the meantime. National Grid has also set up a £530,000 community fund for residents near the Woolavington site. Agratas, the battery arm that will supply JLR, has said its Somerset gigafactory is expected to support around 4,500 jobs once it is fully operational. That figure is for the factory itself, not the substation build, but the two are directly linked: without the grid connection, the plant cannot run at scale.
Why it matters
This is a clean example of what the electrification drive actually looks like on the ground. A gigafactory needs power at industrial scale, and that means new transmission infrastructure gets built alongside it, often years in advance and running years behind, hence the interim 33kV workaround. National Grid has a long pipeline of similar 400kV substation projects feeding data centres, battery plants and the wider decarbonisation push, and Woolavington is a useful marker of how long these builds run: roughly four years from early works to energisation.
For the South West, this sits alongside the existing Hinkley Point C connection works in the same county, meaning sustained demand for high-voltage transmission skills in one region for the rest of this decade.
What it means for your career
Power transmission is one of the few corners of UK construction where the order book is getting longer, not shorter, and Balfour Beatty's utilities arm is one of several contractors scaling up delivery teams to match. If you have substation, high-voltage cabling or grid connection experience, Somerset and the wider South West grid corridor is worth watching closely over the next few years, not just for site roles but for the commercial and planning teams managing a pipeline of similar projects elsewhere in the country.
It is also a reminder that gigafactories and data centres do not just create factory floor jobs. Every one of them drags a multi-year civils and power infrastructure programme behind it, and those programmes need QSs, project managers and planning engineers long before the client's own headcount figures start making headlines.