HS2 engineers have completed the first phase of launching the Duddeston Junction Viaduct over the Birmingham to Derby railway lines, HS2 confirmed this week. It is the first and longest of five interconnecting structures, known as the Curzon Approaches, that carry the line into Birmingham's Curzon Street station. The team has launched the first 170 metres of a 700 metre structure over two freight lines, the opening move in an operation that will eventually cross six railway tracks, three freight and three passenger, and is not due to finish until next summer.
The numbers give a sense of the job. The viaduct follows a curved horizontal alignment on a three per cent gradient, rising to sit 12 metres above the existing tracks. It is built from weathering steel in fourteen spans of around 55 metres each, and will weigh close to 6,835 tonnes once complete. The next launch phase, over the live passenger lines, is scheduled to begin in December, which means this is a live railway crossing being built over trains that keep running underneath it.
Why it matters for the market
This is the kind of story that can read as just another HS2 milestone, but the shape of the work is the point. A launch of this size and complexity, over live freight and passenger lines, needs a sustained team on site for the best part of a year, not a short mobilisation. It sits alongside the news that HS2's civil engineering between Old Oak Common and Curzon Street is targeted for substantial completion by 2029, so Birmingham is entering a phase where structural work gives way to systems, fit-out and testing on the sections already built, while approach structures like this one are still in full swing.
For the West Midlands supply chain specifically, this keeps specialist heavy civils and rail possession work concentrated in the region for at least another twelve months, at a point when the national civil engineering PMI reading has just posted its worst month since October 2020. HS2's Birmingham programme is one of the few pockets of the civils market still visibly ramping rather than winding down.
What it means for your career
For engineers with rail possession experience, or anyone who has worked live-line crossings, this is a live vacancy signal even without a job advert to point to. Work of this complexity pulls in temporary works engineers, rail systems specialists and site management with major structures experience, and the December start of the passenger line crossing is a fixed date that contractors will be resourcing against now.
It is also worth noting for anyone earlier in their career and weighing whether rail is still worth specialising in. The headline PMI numbers on civil engineering are weak, but they are an average across the whole sector. Programme-specific pockets like Curzon Approaches are still hiring on their own timetable, disconnected from the wider market mood. If you are Birmingham-based or willing to relocate for eighteen months, this is one of the more concrete openings in a market that is otherwise short of them.